Activity a m b
Immediate Predecessor(s)
A 2 6 8 -
B 10 11 12 -
C 1 2 3 -
D 6 7 8 C
E 2 4 6 B, D
F 1 2 3 A, E
G 7 11 13 A,
E
H 11 12 13 F
I 5 7 9 G
J 14 16 18 C
K 4 8 12 H, I
a) find expected time and variance
EXPECTED TIME = (OPTIMISTIC TIME + (4 * MOST LIKELY TIME) + PESSIMISTIC TIME) / 6
VARIANCE = ((PESSIMISTIC TIME - OPTIMISTIC TIME) / 6)^2
|
ACTIVITY |
EXPECTED TIME |
VARIANCE |
|
A |
(2 + (4 * 6) + 8) / 6 = 5.67 |
((8 - 2) / 6)^2 = 1 |
|
B |
(10 + (4 * 11) + 12) / 6 = 11 |
((12 - 10) / 6)^2 = 0.11 |
|
C |
(1 + (4 * 2) + 3) / 6 = 2 |
((3 - 1) / 6)^2 = 0.11 |
|
D |
(6 + (4 * 7) + 8) / 6 = 7 |
((8 - 6) / 6)^2 = 0.11 |
|
E |
(2 + (4 * 4) + 6) / 6 = 4 |
((6 - 2) / 6)^2 = 0.44 |
|
F |
(1 + (4 * 2) + 3) / 6 = 2 |
((3 - 1) / 6)^2 = 0.11 |
|
G |
(7 + (4 * 11) + 13) / 6 = 10.67 |
((13 - 7) / 6)^2 = 1 |
|
H |
(11 + (4 * 12) + 13) / 6 = 12 |
((13 - 11) / 6)^2 = 0.11 |
|
I |
(5 + (4 * 7) + 9) / 6 = 7 |
((9 - 5) / 6)^2 = 0.44 |
|
J |
(14 + (4 * 16) + 18) / 6 = 16 |
((18 - 14) / 6)^2 = 0.44 |
|
K |
(4 + (4 * 8) + 12) / 6 = 8 |
((12 - 4) / 6)^2 = 1.78 |
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 6 8 10 — G 3 3 5 C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 D, G,...
Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H A, C, F, G A, C, E, H How much...
Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
activity preceding optimistic probability pessimistic a -- 7 9 14 b a 2 2 8 c a 8 12 16 d a 3 5 10 e b 4 6 8 f b 6 8 10 g c,f 2 3 4 h d 2 2 8 i h 6 8 16 j g,i 4 6 14 k e,j 2 2 5 a. What is the estimated time of completing the project if the critical path is A-D-H-I-J-K? b. calculate the project...
Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float Activity description immediate predecessor Expected time (Weeks) A - 5 B - 4 C A 7 D B 7 E B 8 F B 5 G C,D 8 H E,I 11 I F 2 J F 12 K H,I 11 2.convert the above into activity on the node
From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.
2. Consider the network described in the table below. Immediate Predecessor(s) Activity J K L M N O Р Pessimistic 15 9 10 3 9 10 10 J J KM KM LN Probable 10 8 6 3 5 7 8 Optimistic 8 7 5 3 1 4 3 Draw the network diagram and answer the following questions, DuC duUCULUU AabbLCU AOBOLcud Red E 1 Normal 1 No Spac... Heading 1 Heading 2 Title Subtitle Subtle Em... Sel Styles Edit Paragraph...
Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 8 B A 4 C A 4 D C 8 E B, D 2 F D 6 G E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....