Question

Which action would guarantee an improvement in overall project​ duration? A. employ the agile project management...

Which action would guarantee an improvement in overall project​ duration? A. employ the agile project management approach B. document the project using an​ Activity-on-Node diagram C. add dummy activities to the project to​ off-set long duration task steps D. reduce the duration time of a task on the critical path E. convert the project from CPM to PERT project management

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The answer is given below:

D. reduce the duration time of a task on the critical path.

One important way to improve project schedule is through determining the critical path in order to focus on the delivery on time by cutting its duration and completing the same ahead of its schedule.

Add a comment
Know the answer?
Add Answer to:
Which action would guarantee an improvement in overall project​ duration? A. employ the agile project management...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which one is not correct about the critical path method (CPM) in project management? Duration of...

    Which one is not correct about the critical path method (CPM) in project management? Duration of a project is equal to the duration of its critical path. There could be more than one critical paths. Crashing a project is shortening the duration of the critical activities. The tasks on the critical path can be delayed without delaying the project duration. Slack times of activities on a critical path are zero.

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

  • Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

    Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...

  • A) We require you to describe how you would use project management tools to develop and implement...

    A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: project management software Gantt and bar charts critical path method (CPM) Program Evaluation Review Technique charts (PERT) cost schedule control system life cycle cost analysis logistics support analysis spreadsheets technical resources B) Whilst completing your project plan, ensure you include the following: deliverables   work breakdown budget and allocation of resources      timelines risk management...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • 6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date:...

    6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date: Wednesday 6/11/2019 ( Total Raw Paints 20 Objective: This assignment is intended to provide you with an opportunity o e scheduling network analysis techniques using CPM and PERT.Ih sllaborations.of ans kindwill.nteeleatel dge and skils in id igmentand Examine the Sollewing table of activities, with stochastic (peobabilistic) dution estimates and predecessoe information (duration estimates are in eck) for a small peoject AtyOpin M yPi Predeo...

  • •Please help develop an overall delivery Process using the below to be in line with Agile project...

    •Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...

  • 2. A) We require you to describe how you would use project management tools to develop and implement a project plan. Dis...

    2. A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?) Responsible person (Who will do it?) When? Budget Acquire additional resources – delivery van. To provide a delivery service and provide brand recognition Purchase a new van for...

  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • re not connected a) Scheduling-CEEI369].pcxl+ ﹀ cal/Packages/microsoft windowscommunicationsapps Bwekyb3d8bbwe/LocalState/Files/so/187/Sche CES-CEE Scheduling Pick a Civil Engineering Project...

    re not connected a) Scheduling-CEEI369].pcxl+ ﹀ cal/Packages/microsoft windowscommunicationsapps Bwekyb3d8bbwe/LocalState/Files/so/187/Sche CES-CEE Scheduling Pick a Civil Engineering Project and divide it into a reasonable number of tasks (10) to make this an interesting, but not onerous, assignment. Turn in (1) a Task Table like the one I used to introduce the in-class scheduling problem, (2) an Arrow Diagram (showing completed passes and critical path), (3) a Gantt Chart (common bar chart), and (4) a Modified Bar Chart. No Resource leveling or crashing!...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT