Question

Which one is not correct about the critical path method (CPM) in project management? Duration of...

Which one is not correct about the critical path method (CPM) in project management? Duration of a project is equal to the duration of its critical path. There could be more than one critical paths. Crashing a project is shortening the duration of the critical activities. The tasks on the critical path can be delayed without delaying the project duration. Slack times of activities on a critical path are zero.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. D. The tasks on the critical path can be delayed without delaying the entire project.


Critical path method works on the assumptions that there is a particular chain which has the longest duration and slack value of 0. Since we have made the following assumptions, we can say that any slack introduced to the chain would end up increasing the duration of the project.


**PLEASE RATE THE ANSWER WITH A POSITIVE FEEDBACK

Add a comment
Know the answer?
Add Answer to:
Which one is not correct about the critical path method (CPM) in project management? Duration of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...

    Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...

  • Question 92 In CPM, the duration of the project o a. is determined by managers o...

    Question 92 In CPM, the duration of the project o a. is determined by managers o b.is determined by a supervising government agency oc. is equal to the duration of the critical path o d. is determined by investors Question 90 Slack for activity I is computed as oa. EST; - LST; o b. EFT; - LFT; oc. LFT; - EST; od. LST; - EST; Question 88 A project plan is established o a. before project activities begin o b....

  • A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity...

    A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

  • Which action would guarantee an improvement in overall project​ duration? A. employ the agile project management...

    Which action would guarantee an improvement in overall project​ duration? A. employ the agile project management approach B. document the project using an​ Activity-on-Node diagram C. add dummy activities to the project to​ off-set long duration task steps D. reduce the duration time of a task on the critical path E. convert the project from CPM to PERT project management

  • Problem 5. For the diagram below find the critical path, the duration of the project, and...

    Problem 5. For the diagram below find the critical path, the duration of the project, and calculate the slack for each task, including each tasks' ES, EF, LS and LF 2 8 113 912 4 6 12 4 6 10

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT