The following table shows the PPB (Part Period Balancing) calculation for an MRP lot sizing problem. If EPP (Economic Part Period) is 200, weekly holding cost per unit is $1 and set up cost is $200, what will be the total cost?
| Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Month Requirement | 100 | 150 | 200 | 150 | 100 | 150 | 250 |

A) $450
B) $600
C) $1050
D) $1250
E) None of the above
|
Alternative |
Order Cost |
Carrying Cost |
Remarks |
|
Order 100 to cover the needs of period 1 |
200 |
50 |
Continue until carrying costs pass order cost |
|
Order 250 to cover the needs of periods 1 and 2 |
200 |
125 |
Continue until carrying costs pass order cost |
|
Order 450 to cover the needs of periods 1, 2 and 3 |
200 |
225 |
Stop as carrying costs are larger than order cost |
|
Decision: since 225 is closer to 200 than 125 is, order 450 to cover the needs of periods 1, 2 and 3 |
|||
|
Order 100 to cover the needs of periods 4 |
200 |
75 |
Continue until carrying costs pass order cost |
|
Order 250 to cover the needs of periods 4 and 5 |
200 |
125 |
Continue until carrying costs pass order cost |
|
Decision: order 250 to cover the needs of periods 4 and 5 |
|||
|
Order 150 to cover the needs of period 6 |
200 |
75 |
Continue until carrying costs pass order cost |
|
Order 400 to cover the needs of periods 6 and 7 |
200 |
200 |
Continue until carrying costs pass order cost |
|
Total cost is = 200+225+200+125+200+200 = 1150 |
|||
The following table shows the PPB (Part Period Balancing) calculation for an MRP lot sizing probl...
sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...
The following is a partial MRP table. Based on the information provided, an inventory holding cost of $0.39 per unit per week and a setup cost of $139 per order, what would be the planned order release for week 2 using a part period balancing lot sizing approach? Week Gross Requirements Scheduled Receipts On-Hand Inventory Net Requirements Time Phased Net Requirements Planned Order Releases 0 1 2 3 4 5 10 30 20 15 20 40 L | 10 40...
Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c) multiples...
4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c)...
Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan Week 1 2 3 4 5 6 8 10 11 12 7 Gross requirements 20 40 40 70 30 10 80 40 Also, for this plan the Holding cost $2.50/unit/week; setup...
Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan. Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 40 60 20 10 80 40 Also, for this plan the Holding cost =$2.50/unit/week;...
Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an MRP for their cell phone cameras with a minimum cost possible. The following table show gross requirements of the product Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the MRP. 2 4 8 11 Period Gross requirements 1 20 3 40 5 40 6 60 7 30 9 20 10 70 12 50 Also, for this plan the...
Given the following MRP matrix for Item Z, prepare a material requirements plan for component P. Lot-for-lot ordering will be used for component P. ITEM: Z Lot Size: Q=100 LT: 1 Project on Hand : 200 Period 1 2 3 4 5 6 7 Gross Requirements 600 300 270 200 Schedule Receipts 250 150 Project on Hand 200 Net Requirements Planned Order Receipts Planned Order Releases ps fr unit 1 is 100 and i do not have the tree
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 23 4 5 6 7 89 10 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost $1.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period 1 2 3 45 6 7 8 9 10 111 Gross requirements 30 40 40 70 20 10 80...
American Electronics produces Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like to create an MRP for their Tough-Robot with a minimum cost possible for the plan. The following table show gross requirements of Tough-Robot for ten weeks. You are asked to develop a solution using an ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100) as a Lot Sizing technique. What is the cost of...