Question

The following table shows the PPB (Part Period Balancing) calculation for an MRP lot sizing problem. If EPP (Economic Part Period) is 200, weekly holding cost per unit is $1 and set up cost is $200, what will be the total cost?

Month 1 2 3 4 5 6 7
Month Requirement 100 150 200 150 100 150 250

0 0 vo 5 50550550 5 3 2 5 0 42341 2 3 5 2 4 ー ,23 .. 45.. 67 3 3

A) $450

B) $600

C) $1050

D) $1250

E) None of the above

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Alternative

Order Cost

Carrying Cost

Remarks

Order 100 to cover the needs of period 1

200

50

Continue until carrying costs pass order cost

Order 250 to cover the needs of periods 1 and 2

200

125

Continue until carrying costs pass order cost

Order 450 to cover the needs of periods 1, 2 and 3

200

225

Stop as carrying costs are larger than order cost

Decision: since 225 is closer to 200 than 125 is, order 450 to cover the needs of periods 1, 2 and 3

Order 100 to cover the needs of periods 4

200

75

Continue until carrying costs pass order cost

Order 250 to cover the needs of periods 4 and 5

200

125

Continue until carrying costs pass order cost

Decision: order 250 to cover the needs of periods 4 and 5

Order 150 to cover the needs of period 6

200

75

Continue until carrying costs pass order cost

Order 400 to cover the needs of periods 6 and 7

200

200

Continue until carrying costs pass order cost

Total cost is = 200+225+200+125+200+200 = 1150

Add a comment
Know the answer?
Add Answer to:
The following table shows the PPB (Part Period Balancing) calculation for an MRP lot sizing probl...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...

    sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...

  • The following is a partial MRP table. Based on the information provided, an inventory holding cost...

    The following is a partial MRP table. Based on the information provided, an inventory holding cost of $0.39 per unit per week and a setup cost of $139 per order, what would be the planned order release for week 2 using a part period balancing lot sizing approach? Week Gross Requirements Scheduled Receipts On-Hand Inventory Net Requirements Time Phased Net Requirements Planned Order Releases 0 1 2 3 4 5 10 30 20 15 20 40 L | 10 40...

  • Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the...

    Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c) multiples...

  • 4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and...

    4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c)...

  • Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven...

    Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan Week 1 2 3 4 5 6 8 10 11 12 7 Gross requirements 20 40 40 70 30 10 80 40 Also, for this plan the Holding cost $2.50/unit/week; setup...

  • Best-Appliance makes​ high-powered industrial strength microwave oven and wants to create an MRP for their oven...

    Best-Appliance makes​ high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing​ (PPB) solution and calculate the total relevant costs for the plan.        Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 40 60 20 10 80 40 ​Also, for this plan the Holding cost =​$2.50​/unit/week;...

  • Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an...

    Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an MRP for their cell phone cameras with a minimum cost possible. The following table show gross requirements of the product Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the MRP. 2 4 8 11 Period Gross requirements 1 20 3 40 5 40 6 60 7 30 9 20 10 70 12 50 Also, for this plan the...

  • Given the following MRP matrix for Item Z, prepare a material requirements plan for component P....

    Given the following MRP matrix for Item Z, prepare a material requirements plan for component P. Lot-for-lot ordering will be used for component P. ITEM: Z        Lot Size: Q=100 LT: 1 Project on Hand : 200 Period 1 2 3 4 5 6 7 Gross Requirements 600 300 270 200 Schedule Receipts 250 150 Project on Hand              200 Net Requirements Planned Order Receipts Planned Order Releases ps fr unit 1 is 100 and i do not have the tree

  • Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Per...

    Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 23 4 5 6 7 89 10 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost $1.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period 1 2 3 45 6 7 8 9 10 111 Gross requirements 30 40 40 70 20 10 80...

  • American Electronics produces​ Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like...

    American Electronics produces​ Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like to create an MRP for their​ Tough-Robot with a minimum cost possible for the plan. The following table show gross requirements of​ Tough-Robot for ten weeks. You are asked to develop a solution using an ordering system that always orders 100 units the week prior to a shortage​ (a fixed order quantity of​ 100) as a Lot Sizing technique. What is the cost of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT