The managers of the Frigid Midget Widget (FMW) Company, makers
of small frozen widgets, have listed the tasks that must be
completed to assemble one midget frigid widget (see following
table). The managers must decide how large a crew to assign to each
task; the size of the crew will determine the duration of the task
(generally, there is an inverse relationship between crew size and
job duration). Each job can be assigned a crew of minimum size,
normal size, or maximum size; no other choices are possible for
technological reasons. In addition, union regulations require that
an assigned crew cannot be changed for the duration of the task
(e.g., they cannot assign a normal size crew for the first two days
of a task and then increase the crew size for the remaining
duration of the task). Task durations are merely equal to the total
number of worker-days divided by the crew size assigned to the
task. For example, if a normal crew is assigned to task A, then
that task will require eight days to complete. The FMW Company has
a contract to produce one frigid midget widget every twenty-four
days. Assuming that all workers can perform all tasks, determine
how the production tasks should be scheduled in order to minimize
the workforce needed (hiring and firing costs are very high in this
industry). 
| Task | Predecessor | Total Worker Days | Crew | Duration (Worker Days/Crew) | Using Formula (TE=(To+4Tm+Tp)/6) | Duration | Manpower Required | Revised Duration | Crew Required | Nature | ||||
| Minimum | Normal | Maximum |
Minimum (Optimistic) |
Normal (Most Likely) |
Maximum (Passimistic) |
|||||||||
| Start | ||||||||||||||
| A | Start | 32 | 2 | 4 | 8 | 16 | 8 | 4 | 9 | 8 | 4 | 4 | 8 | Critical |
| B | Start | 48 | 4 | 6 | 8 | 12 | 8 | 6 | 8 | 8 | 6 | 8 | 6 | |
| C | A | 40 | 4 | 5 | 8 | 10 | 8 | 5 | 8 | 8 | 5 | 5 | 8 | Critical |
| D | A | 12 | 2 | 3 | 4 | 6 | 4 | 3 | 4 | 4 | 3 | 4 | 3 | |
| E | D | 30 | 3 | 5 | 6 | 10 | 6 | 5 | 7 | 6 | 5 | 6 | 5 | |
| F | B,C | 54 | 3 | 6 | 9 | 18 | 9 | 6 | 10 | 9 | 6 | 9 | 6 | Critical |
| G | E,F | 24 | 3 | 4 | 6 | 8 | 6 | 4 | 6 | 6 | 4 | 6 | 4 | Critical |
| End | G | |||||||||||||
| Notes | ||||||||||||||
| Since Can be done only from Minimum or Normal or Maximum so if Duration is not from above same shall be adjusted among Three options | ||||||||||||||
| Critical Path Shall be A-C-F-G due to High Duration | ||||||||||||||
| A-D-E-G | 24 | |||||||||||||
| A-C-F-G | 31 | |||||||||||||
| B-F-G | 23 | |||||||||||||
| Since Project needs to be done with in 24 Days crashed duration to 24 Days by reducing duration of A and C by 4 and 3 Days Respectively | ||||||||||||||
| Revised Duration | ||||||||||||||
| A-D-E-G | 20 | |||||||||||||
| A-C-F-G | 24 | |||||||||||||
| B-F-G | 23 | |||||||||||||
| Since Critical Path Can not be postponed Max number of Crew required 8Mem and B needs be started with max 1Day Delay | ||||||||||||||
| Resource Aloocation as follows Max Crew Required 14Mem | ||||||||||||||
| Crew | 4th | 8th | 9th | 11th | 12th | 17th | 18th | 24th | ||||||
| 1 | A | C | F | G | ||||||||||
| 2 | ||||||||||||||
| 3 | ||||||||||||||
| 4 | ||||||||||||||
| 5 | Idle | |||||||||||||
| 6 | ||||||||||||||
| 7 | Idle | E | ||||||||||||
| 8 | ||||||||||||||
| 9 | B | D | ||||||||||||
| 10 | ||||||||||||||
| 11 | ||||||||||||||
| 12 | Idle | |||||||||||||
| 13 | ||||||||||||||
| 14 | ||||||||||||||
The managers of the Frigid Midget Widget (FMW) Company, makers of small frozen widgets, have listed...
I have this case study to solve. i want to ask which
type of case study in this like problem, evaluation or decision? if
its decision then what are the criterias and all?
Stardust Petroleum Sendirian Berhad: how to inculcate the pro-active safety culture? Farzana Quoquab, Nomahaza Mahadi, Taram Satiraksa Wan Abdullah and Jihad Mohammad Coming together is a beginning; keeping together is progress; working together is success. - Henry Ford The beginning Stardust was established in 2013 as a...
THE COMPANY: MORE POWER, INC. More Power, Inc., is a large, local retail store specializing in the sale and service of hardware, tools, lawn and garden implements, and other materials for the home. More Power operates seven days a week, dawn to dusk. Approximately 120 employees work in distinct divisions within the store, including customer service/return desk; warehouse and delivery; service and repair; and three distinct sections focused on (1) hardware and tools, (2) lawn and garden and outdoors, and...
What an Executive Summary Is
An executive summary is a specific type of document that does
two things: it summarizes a research article, and it offers
recommendations as to how information from the article can be
used.
Some long reports can contain an executive summary section, as
indicated in the Pearson handbook.
Write a 2 pahe Executive Summary
In business contexts, an executive summary is always written
for a specific purpose: to explain the information in the article
to a...
How can we assess whether a project is a success or a
failure?
This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...