  1. The managers of the Frigid Midget Widget (FMW) Company, makers of small frozen widgets, have listed the tasks that must be completed to assemble one midget frigid widget (see following table). The managers must decide how large a crew to assign to each task; the size of the crew will determine the duration of the task (generally, there is an inverse relationship between crew size and job duration). Each job can be assigned a crew of minimum size, normal size, or maximum size; no other choices are possible for technological reasons. In addition, union regulations require that an assigned crew cannot be changed for the duration of the task (e.g., they cannot assign a normal size crew for the first two days of a task and then increase the crew size for the remaining duration of the task). Task durations are merely equal to the total number of worker-days divided by the crew size assigned to the task. For example, if a normal crew is assigned to task A, then that task will require eight days to complete. The FMW Company has a contract to produce one frigid midget widget every twenty-four days. Assuming that all workers can perform all tasks, determine how the production tasks should be scheduled in order to minimize the workforce needed (hiring and firing costs are very high in this industry). Predecessor Total Worker Days Minimum Normal Maximum Task (1,1) Start A 32 48 B 40 Start Start A A D B,C E,F 12 30 54 F G End

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Task Predecessor Total Worker Days Crew Duration (Worker Days/Crew) Using Formula (TE=(To+4Tm+Tp)/6) Duration Manpower Required Revised Duration Crew Required Nature
Minimum Normal Maximum Minimum
(Optimistic)
Normal (Most Likely) Maximum
(Passimistic)
Start
A Start 32 2 4 8 16 8 4 9 8 4 4 8 Critical
B Start 48 4 6 8 12 8 6 8 8 6 8 6
C A 40 4 5 8 10 8 5 8 8 5 5 8 Critical
D A 12 2 3 4 6 4 3 4 4 3 4 3
E D 30 3 5 6 10 6 5 7 6 5 6 5
F B,C 54 3 6 9 18 9 6 10 9 6 9 6 Critical
G E,F 24 3 4 6 8 6 4 6 6 4 6 4 Critical
End G
Notes
Since Can be done only from Minimum or Normal or Maximum so if Duration is not from above same shall be adjusted among Three options
Critical Path Shall be A-C-F-G due to High Duration
A-D-E-G 24
A-C-F-G 31
B-F-G 23
Since Project needs to be done with in 24 Days crashed duration to 24 Days by reducing duration of A and C by 4 and 3 Days Respectively
Revised Duration
A-D-E-G 20
A-C-F-G 24
B-F-G 23
Since Critical Path Can not be postponed Max number of Crew required 8Mem and B needs be started with max 1Day Delay
Resource Aloocation as follows Max Crew Required 14Mem
Crew 4th 8th 9th 11th 12th 17th 18th 24th
1 A C F G
2
3
4
5 Idle
6
7 Idle E
8
9 B D
10
11
12 Idle
13
14
Add a comment
Know the answer?
Add Answer to:
The managers of the Frigid Midget Widget (FMW) Company, makers of small frozen widgets, have listed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • I have this case study to solve. i want to ask which type of case study...

    I have this case study to solve. i want to ask which type of case study in this like problem, evaluation or decision? if its decision then what are the criterias and all? Stardust Petroleum Sendirian Berhad: how to inculcate the pro-active safety culture? Farzana Quoquab, Nomahaza Mahadi, Taram Satiraksa Wan Abdullah and Jihad Mohammad Coming together is a beginning; keeping together is progress; working together is success. - Henry Ford The beginning Stardust was established in 2013 as a...

  • THE COMPANY: MORE POWER, INC. More Power, Inc., is a large, local retail store specializing in...

    THE COMPANY: MORE POWER, INC. More Power, Inc., is a large, local retail store specializing in the sale and service of hardware, tools, lawn and garden implements, and other materials for the home. More Power operates seven days a week, dawn to dusk. Approximately 120 employees work in distinct divisions within the store, including customer service/return desk; warehouse and delivery; service and repair; and three distinct sections focused on (1) hardware and tools, (2) lawn and garden and outdoors, and...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT