CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram fo
13-19. Do you understand PERT charts? Refer back to Figure 13-11 and answer the following questions: a. Which activity or act
0 0
Add a comment Improve this question Transcribed image text
Answer #1
a. Before activity to begin activity B should be completed.
b.Activities A,E or B,F should be completed to begin activity G.
c.All the activities that is Activity A,B,C,D,E,F,G,H,I should be completed in order to begin activity J.
d.Five Paths through the network are
1.1→4→5→6→7→8
2.1→4→5→7→8
3.1→2→5→6→7→8
4.1→2→5→7→8
5.1→2→3→7→8
e.activity F can be completed only after completing activity b which takes 14.
so earliest start time for activity F is 14
f.Activity G can be completed in two paths and the time taken are
path1. 1→2→5 this path takes 11(4+7)
path2. 1→4→5 this path takes 18(11+1)
so earliest start time of Activity G is 11 (Path1)
g.five paths are possible for J and time taken for each path is
       Path1.1→4→5→6→7 Time Taken:29 (17+1+6+5)
Path2.1→4→5→7    Time Taken:24(17+1+6)
Path3.1→2→5→6→7    Time Taken:32 (14+7+6+5)
Path4.1→2→5→7    Time Taken:30(14+7+9)
Path5.1→2→3→7    Time Taken:22 (14+2+6)
Earliest time for which activity J can be completed is Path5 (Time=22)
h. 2 paths are possible to complete Activity G as follows
       Path1. 1→4→5             Time Taken:18(17+1)
      Path2.1→2→5               Time Taken:21(14+7)
i.Slack time for Activity G
        =Late start time -Earliest start time
         =21-18=3
Add a comment
Know the answer?
Add Answer to:
please answer from a until i with the solving steps CHAPTER 13 / Developing and implementing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network...

    CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Activity Prepare the Physical site 3958 Determine functional changes Select and assign personnel Train personnel Acquire and install computer equipment Establish...

  • .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc repres...

    .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...

  • 1. State whether each of the following statement is true or false. a) The sequence of...

    1. State whether each of the following statement is true or false. a) The sequence of activities in a project is depicted by the precedence (0.5 mark) (0.5 mark) relationships. The critical path is the shortest path through the project network. Slack is the amount of time an activity can be delayed without delaying the project. In PERT, three time estimates (optimistic, most likely and pessimistic) provide an estimate of the mean and variance for each activity based on the...

  • Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...

    Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no

  • Consider the following project. Activity ImmediateActivity Time (days) Predecessor CD E,F What is the critical path? O ACFG O ADFG OBEG ACDFG What is the latest finish time for activity F? 0 9 O...

    Consider the following project. Activity ImmediateActivity Time (days) Predecessor CD E,F What is the critical path? O ACFG O ADFG OBEG ACDFG What is the latest finish time for activity F? 0 9 O 13 O 16 What is the latest possible time that Activity E can be started without delaying the completion of the project? What is the latest time that activity B can finish without delaying any other activities? 4 What is the latest time that activity B...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • 20 The late finish time (LF) is a the latest possible date an activity can be...

    20 The late finish time (LF) is a the latest possible date an activity can be completed without delaying the project's completion b c the maximum extent to which an activity can be delayed the latest possible date an activity can be completed before the activity becomes irrelevant d the latest possible time an activity can be completed on a given day 21 A critical path a is the longest individual path in a network b is the path of...

  • Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is ver...

    Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is very urgent Question 7 The Family Entertainment Group is about to begin the production of its most Ebo Whyte, ensive) movie of the year. The movie's producer, Mr. project. He has identified the eight major activities (labe and H) rcquired to produce the movie. Activities weeks respectively, cannot start until activity A completed. Activities E and F tak...

  • Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End...

    Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)

  • Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37...

    Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT