5. All of the following are true about projects and operations EXCEPT: A Operations are ongoing endeavours that produce repetitive outputs, with resources assigned to do basically the same set of tasks according to the standards institutionalzed in a product life cycle, whereas projects are temporary endeavours Projects require project management activities and skill sets, whereas operations require business process management, operations management activities, and skill sets. Projects can intersect with operations at various points during the product life cycle. At each point, deliverables and knowledge are transferred between the project and operations for mplementation of the delivered work. B. C. D. Because of their temporary nature, projects cannot help achieve an organizations long term goals. Therefore, strategc activties in the organization can be generally addressed w thin the organizations normal operations. 7. Your job responsibility is to align components Iprojects, programs, or related operationst to the organ zational strategv, organized into portfolios or subsidlary portfolios to optimize project or program objectives, dependencles, costs, timelines, benefits, resources, and risks. This is known as: A Components management B. Process management C. Program management D. Portfolio management. 8. The PMBOK Gulde is the standard for: A Managing all projects all of the time. 8. Managing all projects most of the time. C. Managing most projects most of the time. D. g some projects some of the time 9. The collection of generally sequental and sometimes overlapping project phases, whose name and number are determined by the management and control needs of the organlzation or organ zations involved in the project, is known as the: A 8. C. Project waterfall. Project life cycle. Project life stages. Project Management Process Groups. 10. All of the following are true about project phases and the project life cycle EXCEPT A Stakeholder influences, risk, and uncertainty are greatest at the start of the project. These factors decrease over the life of the project. 8. The ablility to influence the final characteristics of the projects product, without significantly mpacting cost, is highest at the start of the project and decreases as the project progresses toward completion.
11. All of the following statements about the project life cycle and the product life cycle are true EXCEPT A. In the project predictive lie cycle, the project scope and the time and cost required to B. In the project iterative and incremental life cycles, project phases intentionally repeat one or C The product life cycle is the series of phases that represent the evolution of a praduct, from D. The produet life cycle is contained within the predictive praject life cycle. deliver that scope are determined as early in the project life cycle as practically passible. more project activities as the project tearms understanding of the product increases concept through delivery, growth, maturity, and to retirement. 12. You are managing a project in which you intend to respond to high levels of change and ongoing stakeholder invovement. The most suitable project life cycle far your project is the: A. Predictive life cycle B. Adaptive life cycle C Waterfall life cycle. D. Configuration management life cycle. 13. The five Project Management Process Groups are: A. Planning, Checking, Directing, Monitoring, and Recording. B. Initiating. Planning, Executing, Monitoring and Controlling, and Closing. C Planning, Executing, Directing, Closing, and Commissioning. D. Initiating. Executing, Monitoring, Evaluating, and Clasing. 14. Project Management Processes A. May be overlapping activities that occur throughout the project B. May be overlapping activities that generally occur at the same level of intensity within each phase of the project. C Aregenerally discrete, one-time events. D. Are discrete, repetitive events that occur generally at the same level of intensity throughout each phase of the project.
16. For a project to be successful, the project should generally achieve all of the following EXCEPT: A. B. C. Achieving stakeholder satisfaction. Striving to obtain acceptable customer/end-user adoption. Appling knowledge, skills, and processes within the Project Management Process Groups uniformly to meet the project objectives Fulfilling other agreed-upon success measures or criteria. D. 17. The project business case is all of the following EXCEPT: Documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities A document that lists the objectives and reasons for project initiation. A document that serves as an important input to the project initiation and is seldom used after the project is approved. An important document that may result in a go/no-go decision for the project. A. B. C. D. 18. The key elements of the benefits management plan are all of the following EXCEPT: A. Work Breakdown Structure B. Benefits owner. C. Assumptions. D. Strategic alignment. 19. A significant amount of data is collected and analyzed throughout the project. All of the following are examples of project data and information EXCEPT: A. 8. C. D. Work performance data. Work performance analysis. Work performance information. Work performance reports.
20. Project tailoring is an important consideration ior most projects. Which of the following is the least likely project consideration? A. Project managers skills and competency 8. Each project is unique. C. Addressing competing constraints. D. Level of project governance varies. 4 Words 떠 Cannot drop at current location , wel 31 MacBook Pro Fa FS F6
15. The linkages between project management processes are best described by the following: A. The work breakdown structure links processes a. Processes are linked by their planned objectives-the summary objective of one often becomes the detailed action plan for another within the project, subproject, or project phase. Processes are linked by the outputs that are produced-the output of one process generally becomes an input to another process or is a deliverable of the project, subproject, or project phase. There are no significant links between discrete processes. C. D. ords P Cannot drop at current location. 31 MacBook Pro
C. D. Project life stages. Project Management Process Groups 10. All of the following are true about project phases and the project life cycle EXCEPT A. Stakeholder influences, risk, and uncertainty are greatest at the start of the project. These factors decrease over the life of the project The ability to influence the final characteristics of the projects product, without significantly impacting cost, is highest at the start of the project and decreases as the project progresses toward completion 8. The cost of changes and correcting errors typically increases substantially as the project approaches completion. Cost and staffing levels are generally steady throughout the project life cycle. c. D. Words PCannot drop at current location 31 MacBook Pro
0 0
Add a comment Improve this question Transcribed image text
Answer #1

I can only answer 1 question at a time so I am solving question 6.

Answer is : D. Because of their temporary nature, projects cannot help achieve an organization's long-term goals. Therefore, strategic activities in the organization can be generally addressed within the organization's normal operations.

It is clear from the very definition of projects and operations that the answer is D.

Please do rate me and mention doubts, if any, in the comments section.

Add a comment
Know the answer?
Add Answer to:
5. All of the following are true about projects and operations EXCEPT: A Operations are ongoing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 25. All af the following are external environmental factors EXCEPT: A Legal restrictions B. Organizational values...

    25. All af the following are external environmental factors EXCEPT: A Legal restrictions B. Organizational values and principles. C. Competitive movements D. Economic conditions. 26. Organizational process assets IOPAs in luence the management of projects. Which one of the following best describes the important categories of OPAs? A Organizational knowledge bases and processes. B. Processes, policies, procedures, tools, and techniques C. Organizational knowledge bases, processes, policies, and procedures. D. Organizational knowledge bases, tools, and techniques 27. The organization's processes and...

  • Question #12 On agile projects, the scope definition begins with: A-Requirements B-large chunks of work, or...

    Question #12 On agile projects, the scope definition begins with: A-Requirements B-large chunks of work, or features C-work packages D: stories and personas Question# 13 Which of the following is an advantage associated with managing projects in a functional organization? A-Traditional department barriers are reduced. B-Combines task focus with technical capability. C- Rapid communication between the various functions working on the project. D-Rapid communication between the various functions working on the project. Question #14 A project communications plan generally includes...

  • QUESTION 8 Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements...

    QUESTION 8 Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. All of the following are true about this process EXCEPT: A. The project's success is directly influenced by active stakeholder involvement in the discovery and decomposition of needs into requirements and by the care taken in determining, documenting, and managing the requirements of the product, service, or result of the project. b. Requirements become the foundation of the Wes. Cost,...

  • Examples of projects for healthcare operations management include all but which of the following? a. Deployment of...

    Examples of projects for healthcare operations management include all but which of the following? a. Deployment of a pharmaceutical ordering and inventory system b. Replacement of a damaged view screen in a picture archiving and communication system c. Design/construction of a new facility or building d. Analysis of patient business processes Which of the following should be considered in the adoption of operational metrics in a hospital? a. The number of metrics should be maximized b. Reporting frequency should be...

  • Which of the following documents discusses how requirements activities will be planned, tracked and changed? a....

    Which of the following documents discusses how requirements activities will be planned, tracked and changed? a. WBS b. Requirements management plan c. Change control plan d. Scope management plan You are developing the project charter. You should consider all of the following as inputs in the Develop Charter process EXCEPT: a. Enterprise Environmental Factors b. Business Case c. Project Management Plan d. Project Statement of Work Your initial list of identified risks will generally have all of the following information...

  • All the following are considered to be benefits of participative budgeting, except for: The budget estimates...

    All the following are considered to be benefits of participative budgeting, except for: The budget estimates are prepared by those in directly involved in activities. Individuals at all organizational levels are included in the process, creating a better communication devise throughout the company. When managers set their own targets for the budget, top management does not need to review and oversee the targets. Managers are held responsible for reaching their goals and cannot easily shift responsibility by blaming unrealistic goals...

  • Project Management Processes Assignment Part I by answering the assigned questions.   Part II by completing the...

    Project Management Processes Assignment Part I by answering the assigned questions.   Part II by completing the matching exercise.   Part III by answering true or false to the questions. Part I – Answer the following questions (30 points): 1.                  Why aren’t the processes groups the same as project phases? (15 points) 2.                  After “create WBS” on a project what would be the next five sequences to             follow? (15 points) Part II – Matching Exercise (20 Points): Match column A with B: (2...

  • A.   True/False/Fill-in-the-blanks T/F.    Gantt chart can be used to visually see when major milestones are, when...

    A.   True/False/Fill-in-the-blanks T/F.    Gantt chart can be used to visually see when major milestones are, when tasks have been completed, the projected length of a task and relationships among all project tasks. T/F. All projects are temporary and undertaken to create a product, service, exceed customer expectation or result that is unique T/F.   The Delphi technique is a quick and economical way to estimate the duration and cost of project activities.   T/F.   A requirements management plan should describe how requirements...

  • You are the project manager for a power plant project. You have completed project initiation activities...

    You are the project manager for a power plant project. You have completed project initiation activities and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete and manage changes to the baseline. What process plan would you choose to perform? A. Develop project management plan B. Develop project management life cycle C. Develop WBS and define scope D. Develop project charter

  • QUESTION 25 Which of the following statements is true about the concept and discipline of operations...

    QUESTION 25 Which of the following statements is true about the concept and discipline of operations management?    Operations management is building strategic, long-term relationships with suppliers and customers.    Finished products of the business can be identified as important inputs into an operations management system.    Operations management is more of a multi-firm (i.e. multi-business) concept than a single-firm concept.    Operations management concerns the design, direction, control and improvement of processes that transform inputs into finished products and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT