Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through F represents an activity, as shown in the accompanying precedence diagram.
The probabilistic time for each activity is as follows
|
Activity |
Time |
Activity |
Time |
|
A |
4-5-6 |
D |
4-5-6 |
|
B |
2-5-6 |
E |
2-5-6 |
|
C |
3-4-5 |
F |
3-4-6 |
What is the expected time and standard deviation of path A-C-D?
What percentage will path A-C-D finish within 13 weeks?
Please type your answer and the steps of computation
To find the expected time, we will use the following formula.
T = (a + 4m + b) / 6
A. (4 + (4 * 5 ) + 6) / 6 = 5
B. (2 + (4 * 5 ) + 6) / 6 = 5
C. (3 + (4 * 4 ) + 5) / 6 = 4
D. (4 + (4 * 5 ) + 6) / 6 = 5
E. (2 + (4 * 5 ) + 6) / 6 = 5
F. (3 + (4 * 4 ) + 6) / 6 = 4
To find the variance, we will use the following formula.
Variance = [(b - a) / 6] ^2
A. [(6 -4) / 6 ] ^ 2 = 0.11
B. [(6 -2) / 6 ] ^ 2 = 0.44
C. [(5 -3) / 6 ] ^ 2 = 0.11
D. [(6 -4) / 6 ] ^ 2 = 0.11
E. [(6 -2) / 6 ] ^ 2 = 0.44
F. [(6 -3) / 6 ] ^ 2 = 0.25
|
ACTIVITY |
OPTIMISTIC |
MOST LIKELY |
PESSIMISTIC |
EXPECTED TIME |
VARIANCE |
|
a |
m |
b |
t = (a + 4 m + b) / 6 |
[(b - a) / 6] ^2 |
|
|
A |
4 |
5 |
6 |
5 |
0.11 |
|
B |
2 |
5 |
6 |
5 |
0.44 |
|
C |
3 |
4 |
5 |
4 |
0.11 |
|
D |
4 |
5 |
6 |
5 |
0.11 |
|
E |
2 |
5 |
6 |
5 |
0.44 |
|
F |
3 |
4 |
6 |
4 |
0.25 |
CPM
The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.
The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the Predecessor activities.
The critical path represents all the activities in a particular chain which have the largest duration and 0 slack for all activities, and due to this fact, any delay in the critical activities can cause a delay for the entire project.
|
ACTIVITY |
DURATION |
PRE 1 |
PRE 2 |
ES |
EF |
LS |
LF |
SLACK |
|
A |
5 |
0 |
5 |
0 |
5 |
0 |
||
|
B |
5 |
0 |
5 |
4 |
9 |
4 |
||
|
C |
4 |
A |
5 |
9 |
5 |
9 |
0 |
|
|
D |
5 |
C |
9 |
14 |
9 |
14 |
0 |
|
|
E |
5 |
B |
5 |
10 |
9 |
14 |
4 |
|
|
F |
4 |
B |
5 |
9 |
10 |
14 |
5 |
CRITICAL PATH & DURATION:
A - C - D = 14
PROBABILITY
CRITICAL VARIANCE = A - C - D = 0.11 + 0.11 + 0.11 = 0.33
STANDARD DEVIATION = SQRT(CRITICAL VARIANCE) = SQRT(0.33) = 0.57
EXPECTED = 13 DAYS
Z = DUE - EXPECTED / STANDARD DEVIATION
Z = 14 - 13 / 0.57 = 1.754
THE Z VALUE OF 1.754 GIVES 0.9603 OR 96.03% PROBABILITY OF COMPLETION.
Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through...
For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO
For the activities given in the table: Draw...
1) Construct an activity on arrow (AOA) network based on the activity description below. Activity Predecessors A - B A C A D A E B, C F E G F H G
Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float Activity description immediate predecessor Expected time (Weeks) A - 5 B - 4 C A 7 D B 7 E B 8 F B 5 G C,D 8 H E,I 11 I F 2 J F 12 K H,I 11 2.convert the above into activity on the node
A project manager discovers that his team has neglected to
complete the network diagram for the project. the network diagram
is shown below. however the project manager has some information
available, specifically that each activity a-g, has a different
duration between one and seven weeks. also the slack time for each
of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F
Given the following table, construct the network diagram, either
AOA or
AON. Times are in days
a. Determine the expected duration of the project.
b.Compute the probability that the project will take at least 18
days.
Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E
Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E
Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...
17-11) Use this network diagram for questions 11 through 17.
1. What is the expected duration of the project? (enter a whole
number)
2. What is the critical path for this project?
3. What is the early finish time for activity E?
4. What is the early start time for activity D?
5. What is the late finish time for activity C?
6. What is the late start time for activity B?
7. What is the slack time for activity...
1) Draw the network diagram (PDM)2) Identify all the paths through the network3) select the critical path and explain why 4) calculate the standard deviation of the critical path ActivityPrecedenceDurationSDANA62BNA10CNA82DNA41EA, B62FC, D62GE62HE, F20JH10KH92LG113MG113NK, L51PM31QK41
a.) Create project network for activites A thru G
b.) Then compute on the network above, the correct Activity on
Arrow format (AOA), the earliest start, earliest finish, latest
start, and latest finish times for project.
a n b b Activity C, E E A Activity А 6 B 2 с 8 D 5 E 6 8 8 12 6 3 9 E Immediate Predecessor(s) G 3 3 5 Н 2 2 2 I 5 5 5 J 4 7...