a task has a normal duration of 12 days and a crash duration of 8 days. its normal cost is $40 and its crash cost is $140. what is the crash cost per day?
Crash cost per day = (Crash cost - Normal cost)/(Normal duration - Crash duration)
= (140-40)/(12-8)
= $ 25 per day
a task has a normal duration of 12 days and a crash duration of 8 days....
Normal Duration "Crashable" Normal Maximum Crash Cos Activity Predecessor (days) Duration Per Day* Days Cost($000s) 000s 2.5 2.0 3.0 2.75 4 4 2,3 4 2 4 3 5,6 7,8 1.5 4 Daily "crashing" costs are added to the normal duration cost
62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20 2 - 3 2 60 60 3 1 4 0 70 0 4 1 2 1 50 10 5 2 5 3 100 60 6 3 2 1 90 100 7 4 5 1 50 30 8 5 2 0 60 40 9 6,7,8 3 1 200 200 Consider the project above. If the indirect costs of the project are:...
Given the project network provided in the attachment, what task or tasks would you crash to reduce the project by one day? What is the cost of the project after you crash the cost by one day? What is the new duration? Please include your excel file with all calculations. Normal Crash Crash Cost Per Day Task Pred Duration Cost Duration Cost a - 5 $ 500 5 $ 500 b a 10 $ 2,000 8 $ 2,400 c a...
Find the optimal way to achieve a project duration of 27 days? Use the template below to record your steps InClass – Project Crashing Exercise Project details: Task Predecessor N (days) C (days) D1 ($) D2 ($) A start 7 5 40 80 B A 9 8 60 70 C B 12 10 90 150 D start 10 7 60 120 E D 5 4 50 60 F E 10 6 80 140 Fin C, F Find the optimal way...
15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity decessor Time Cost Time Cost $50 200 160 a, c a, c 290 100 180 (a) Draw the network and find the critical path, time, and (b) Calculate the crash cost-per-day (all activities may be (c) Find the optimal way of getting an 18-day delivery (d) Find the optimal way of getting a 16-day delivery (e) Calculate the shortest delivery time for the project....
Question 1:
I)-What is the normal cost of this project?
II)-What is the cost of the project after 2 days shortening?
III)-What is the crashing cost per day for activity G?
Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...
A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...
what is the normal cost of this project?
what is the cost of the project after 2 days shortening?
what is the crashing cost per day for avtivity G?
Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...
3. The network for shooting a TV commercial as shown in the table has a fixed cost of $90 per day but money can be saved by shortening the project duration. Find the least-cost schedule. Normal Time 7 Crash Time 4 Activity Description Cost Increase 1st, 2nd 3"d da $30, 50, 70 40, 45, 65 60, 60 35, 60 Contract personnel Obtain stage props Rent equipment Contract studio Set time and date 12 10 9
3. The network for shooting...
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...