The following type of buffer does not add time to a schedule:
(A) milestone
(B) feeding
(C) project
(D) resource
(E) none of the above
The correct answer is D.
Project buffer helps in protecting the project deadline so a single project buffer is added at the end of the project network between the last activity and project deadline. So, a resource when added does not add time to a schedule.
The following type of buffer does not add time to a schedule: (A) milestone (B) feeding...
What does PMO mean? A. Performance Management Office B. Project Management Overview C. Performance Management Overview D. Project Management Office E. Project Management Objective Which of the following is an important project manager role? A. technical expert B. supervisor C. project sponsor D. micromanager E. communicator What is a milestone? A. a significant event in the project B. a mark on a chart that depicts project progress C. an activity on the critical path D. an activity with an uncertain...
1. A milestone can best be described as: a) A significant event in the project schedule b) An activity in the project that consumes a large amount of project resources and time c) The activities included in the close of a phase or the project 2. Project managers have accountability for project success but can delegate to others the project manager s responsibility for quality. True False 3. To whom would the project manager go first for assigning the resources...
post the answers for the following Mcq's.
NOTE: FYI - 17th question has 4 option in the pic option A and
B is there. option C ) Environmental D ) Mandatory.
2. If you are compressing the project schedule by using a technique that generally does not increase project costs, which of the following techniques are you using? A. Fast tracking B. Crashing C. Resource optimization D. Resource leveling 3. The amount of time a successor activity must wait after...
Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 1 B A 4 C A 3 D B 2 E C, D 5 F D 2 G F 2 H E, G 3 b. What is the critical path? A-B-D-F-G-H A-C-D-F-G A-C-E-H A-B-D-E-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? D, 2 weeks; G, 1 week; and H, 1 week....
17. The types of float in a CPM schedule are a. free Float b. negative Float c. total Float d. independent Float e. all of the above 18. A loop in the schedule means a. circular logic between two activities b. two paths with the same logic c. duplicate activities d. negative float e. a and d 19. Constraints can be define as a. imposed restrictions applied to activities to reflect project requirements that cannot be built into the logic....
Warblers feeding on similar foods in the same trees have demonstrated A. allopatry B. symbiosis C. intense competition between species D. resource partitioning Competition A. is a type of symbiotic relationship B. always negatively effects both competing species C. is also referred to as commensalism D. has the same outcome as a parasite-host relationship
From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.
1- Which of the following is NOT a basic type of fire detection system? A Photoelectric detection sensors B Fixed-temperature C Rate-of-rise sensors D Thermal detection 2 .-Which of the following delivers documented instructions to the individuals who are executing the implementation phase? A resources B project plan C project scope D milestone
***Choose ANY 6 vaccines as long as there is one of each type of the following: toxoid vaccine, attenuated virus vaccine, killed virus vaccine, subunit vaccine, conjugate vaccine; DNA vaccine and then fill out the questions below.*** Find an example of each of the types of vaccines (toxoid vaccine, attenuated virus vaccine, killed virus vaccine, subunit vaccine, conjugate vaccine and DNA vaccine) and answer the following questions. VACCINE #1: _________________________________ a. Describe the disease agent, disease transmission, and disease symptoms:...