Question

A business organisation is trying to improve staff morale and motivation and has decided to replace...

A business organisation is trying to improve staff morale and motivation and has decided to replace the existing staff canteen with a modern cafeteria. The works department has drawn up a detailed list of the various activities that will need to be completed, together with an estimate of how long each activity will take and the sequencing of activities. This information is shown in Table 13.11

List Activity Duration Preceding activities personal requirement
A Purchase construction materials 12 Weeks 3
B Purchase catering equipment needed for new cafeteria 3 Weeks 2
c Appoint supervisory architect 2 weeks 1
d Clear site 3 weeks 3
e Produce final building details 8 weeks C,D 1
f Prepare site for construction 3 weeks E 2
g Construct cafeteria 12 weeks A,F 5
h lnstall utility services 4 weeks G 2
i lnstall catering equipment 4 weeks B,H 2
j Decorate internally 2 weeks B,H 2
k Stock cafeteria 4 weeks I,J 1
l Hire catering staff 8 weeks 2
m Train staff on site 2 weeks I,L 3

(a) Using this information construct a network diagram for the proiect. (b) Identify the critical path. (c) Determine float times for all activities. (d) To try to keep the project within budget it has been decided that ideally no more than five personnel should be involved in the project at any one time. Is this feasible?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) Using this information construct a network diagram for the proiect.

(b) Identify the critical path.

(c) Determine float times for all activities.

(d) To try to keep the project within budget it has been decided that ideally no more than five personnel should be involved in the project at any one time. Is this feasible?

Yes, this is feasible as shown in the attached diagram in the first question

Add a comment
Know the answer?
Add Answer to:
A business organisation is trying to improve staff morale and motivation and has decided to replace...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following activities of a hospital expansion project has been identified in the following table. First,...

    The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • 2. Can the project be completed before construction can begin, which is scheduled 40 weeks later?...

    2. Can the project be completed before construction can begin, which is scheduled 40 weeks later? a. Yes, because the project duration time is 39 weeks. b. No, because the project duration time is 41 weeks. c. No, because the project duration time is 42 weeks. d. Yes, because the project duration time is 40 weeks. 3. Which activities can be delayed without delaying the projection completion time? a. B, D and F b. B, D and G c. A,...

  • The ABC Manufacturing Co. has made a decision to replace an existing production line with new...

    The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished. Activity predecessor Optimistic Most likely Pessimistic Expected A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F...

  • A project manager has compiled a list of major activities that will be required to install...

    A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Z-Table is needed) Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1 N...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • A project manager has compiled a list of major activities that will be required to install...

    A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Use Table B1 and Table B2.) (table B1) (table b2) Immediate Predecessor Estimated Times (weeks) A — 2-4-6                    D A 6-8-10                    E D 7-9-12                    H E 2-3-5                    F A 3-4-8                    G F 5-7-9                    B — 2-2-3                    I B 2-3-6                    J I 3-4-5                    K J 4-5-8                    C...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT