Question

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed...

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity Immediate Predecessor(s) Time (Days)
A

------

2
B

------

5
C

------

1
D

B

10
E

A,D

3
F

C

6
G

E,F

8

a) Develop an AON network for this problem.

b) What is the critical path?

c) What is the total project completion time?

d) What is the slack time for each individual activity?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) First I have prepared Network Diagram in Hand Written Format

the Network Diagram is prepared using Forward and Backward Path Calculation, where all Duration is in Days, Activities have Non Zero Float, can be considered as Near Critical Path or Non Critical Path, here C-F-G and A - E -G both are Non critical Path,

b) From Above Network Diagram, Critical Path is shown with Bold Line and the Critical Path is B-D-E-G, as Activities on this Path have least Float or Zero Float

c) Project Need Minimum 26 Days Time to Finish or Total project completion time = 26 Days

d)

Activity Duration Immediate Predecessor Early Start Early Finish Late Start Late Finish Total Float/Slack Free Float
A 2 - 0 2 13 15 2 NA
B 5 - 0 5 0 5 0 NA
C 1 - 0 1 11 12 11 NA
D 10 B 5 15 5 15 0 0(B)
E 3 A,D 15 18 15 18 0 13(A), 0(D)
F 6 C 1 7 12 18 11 0 ( C)
G 8 E,F 18 26 18 26 0 0 (E), 11(F)
Add a comment
Know the answer?
Add Answer to:
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • er Ginde is developing a program in supply chain management certification for managers. Ginde has listed...

    er Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be ucted. The activities, immediate predecessors, and times appear in the accompanying table: Activity immediate Predecessor(s) Time (days) s exercise contains only parts b, c, and d. The critical activities for the leadership training program development project are The project length for the leadership training program development project...

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Operation management

    The following activities are part of a project to be scheduled using CPM.Activity Immediate predecessors Time(Weeks)A - 6B A 3C A 7D C 2E B,D 4F D 3G E,F 7i) Draw the networkii) What is the critical path?iii) How many weeks will it take to complete the project?iv) How much slack does activity B have?

  • activity immediate processor activity time (days) A - 6 B - 8 C A,B 5 D...

    activity immediate processor activity time (days) A - 6 B - 8 C A,B 5 D B 4 E C 7 F C,D 3 G D 6 H E,F,G 5 Given the following information for a project. SHOW ALL WORK. a) Draw the AON(Activity-On-Node) project network b) Write the estimated slack times for activities A-H c) Identify the critical path d) Determine the total completion time of the project.

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Please provide detailed solutions to the following problem. The estimated times and immediate predecessors for the...

    Please provide detailed solutions to the following problem. The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion...

  • 5.) Consider a project whose activities are listed in the table below. Activity A will have...

    5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as…    Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...

  • Tom Schriber, a director for personnel of Management Resources, Inc., is in the process of designing...

    Tom Schriber, a director for personnel of Management Resources, Inc., is in the process of designing a program that its customers can use in the job-finding process. Some of the activities include preparing resumes, writing letters, making appointments to see prospective employers, researching companies and industries, and so on. Some of the information on the activities is shown in the following table: Days Immediate Predecessors Activity a m b A 8 9 10 __ B 6 7 8 __ C...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT