Consider the following project:
| Task ID | Duration (Days) | Predecessors |
| 2 | 70 | - |
| 3 | 30 | 2 |
| 4 | 120 | 3 |
| 5 | 120 | 2 |
| 6 | 120 | 5 |
| 7 | 120 | 3,6 |
| 8 | 150 | 3,6 |
| 9 | 115 | 3,6 |
| 10 | 130 | 7,9 |
| 11 | 90 | 7,9 |
| 12 | 30 | 7,9 |
| 13 | 120 | 7,9 |
| 14 | 75 | 10 |
| 15 | 30 | 14 |
| 16 | 85 | 6 |
| 17 | 165 | 16 |
| 18 | 90 | 16 |
| 19 | 90 | 17,18 |
| 20 | 20 | 8,11,13,15,19 |
What is the slack for task 8?
Answer:
| step 1 | find early start, and early finish from the start of the project for each activity | ||||
| step 2 | Find Maximum EF and keep it as the LF of last activities. Max of EF's is 685 | ||||
| step 3 | calculate LS for each activity after calculating its EF | ||||
| Activity | Duration, D | Early start, ES=Max of early finish of preceding activities | Early finish, EF = ES + D | Late finish, LF= Min of LS of successor activities | Late start, LS= LF - D | Total slack= LF-EF |
| 2 | 70 | 0 | 70 | |||
| 3 | 30 | 70 | 100 | |||
| 4 | 120 | 100 | 220 | |||
| 5 | 120 | 70 | 190 | |||
| 6 | 120 | 190 | 310 | |||
| 7 | 120 | 310 | 430 | |||
| 8 | 150 | 310 | 460 | 665 | 515 | 205 |
| 9 | 115 | 310 | 425 | |||
| 10 | 130 | 430 | 560 | |||
| 11 | 90 | 430 | 520 | |||
| 12 | 30 | 430 | 460 | |||
| 13 | 120 | 430 | 550 | |||
| 14 | 75 | 560 | 635 | |||
| 15 | 30 | 635 | 665 | |||
| 16 | 85 | 310 | 395 | |||
| 17 | 165 | 395 | 560 | |||
| 18 | 90 | 395 | 485 | |||
| 19 | 90 | 560 | 650 | |||
| 20 | 20 | 665 | 685 | 685 | 665 | 0 |
the slack for task 8 is 205
Consider the following project: Task ID Duration (Days) Predecessors 2 70 - 3 30 2 4...
39. Consider the following project, and answer the next 5 questions based on this data: Task ID Duration (Days) Predecessors 2 70 - 3 30 2 4 120 3 5 120 2 6 120 5 7 120 3,6 8 150 3,6 9 115 3,6 10 130 7,9 11 90 7,9 12 30 7,9 13 120 7,9 14 75 10 15 30 14 16 85 6 17 165 16 18 90 16 19 90 17,18 20 20 8,11,13,15,19 What is the...
62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20 2 - 3 2 60 60 3 1 4 0 70 0 4 1 2 1 50 10 5 2 5 3 100 60 6 3 2 1 90 100 7 4 5 1 50 30 8 5 2 0 60 40 9 6,7,8 3 1 200 200 Consider the project above. If the indirect costs of the project are:...
Given the following information about a small project, Task Duration Immediate Estimates Predecessors A 2 days None B 5 days A C 4 days B D 9 days A E 4 days B & D F 12 days E & C Draw a network diagram. Identify the critical path, earliest start and finish and slack for each task. Using MS Excel, produce a Gantt chart for this project. What would happen if a new estimate for task D increases...
Consider the following project, all durations are in days. Find the critical path and which tasks have slack. What is the probability the project will be done in 50 days? How about in 53 days? Suppose any task can be crashed for up to two days for the same cost per day, but that tasks A and N cannot be crashed at all. Which tasks should be crashed if the project needed to be completed in 45 days with at...
Use the following table to calculate duration (round to 0 decimal places) ID TASK NAME Optimistic Most likely Pessimistic Precedence Duration 1 First 1 2 4 2 Second 3 5 10 1 3 Third 9 11 13 2 4 Fourth 3 5 6 3,8,9 5 Fifth 6 7 8 4,11 6 Sixth 5 6 8 1 7 Seventh 3 5 8 6 8 Eighth 1 2 5 7 9 Ninth 1 3 5 6 10 Tenth 4 5 6 9,8...
Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A C 9 B D 5 B E 7 C, D F 6 D G 4 C H 7 E, F, G Activity Duration ES EF LS LF Float A 5 0 5 0 5 B 7 5 12 5 12 C 9 12 21 12 21 D 5 12 17 16 21 E 7 21 28 21 28 F 6 17 23 22 28...
Find the optimal way to achieve a project duration of 27 days? Use the template below to record your steps InClass – Project Crashing Exercise Project details: Task Predecessor N (days) C (days) D1 ($) D2 ($) A start 7 5 40 80 B A 9 8 60 70 C B 12 10 90 150 D start 10 7 60 120 E D 5 4 50 60 F E 10 6 80 140 Fin C, F Find the optimal way...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
Given the following information, the Available to Promise will show ________. Week 1 2 3 4 Forecast Demand 120 120 120 120 Actual Customer Orders 85 100 35 20 Available to Promise MPS 250 250 a. 130, 130, 130, 130 b. 165, 65, 30, 230 c. 130, 10, -110, 130 d. 30, 0, 0, 230
Consider the following information about a small project:
Task
Duration Estimates
ImmediatePredecessors
A
2
days
None
B
3
days
A
C
3
days
B
D
4
days
A
E
1
day
B & D
F
9
days
E & C
b-1. Identify the critical path.
A-B-C-F
A-B-E-F
A-D-E-F
b-2. Identify the earliest start and finish,
and slack for each task. (Leave no cells blank - be certain
to enter "0" wherever required.)
c. Which of these activities should the project...