You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)
Multiple Choice
40
13
45
29
53
FORMULA:
DUE DATE = EXPECTED COMPLETION TIME + (Z * STDEV)
Expected time = 40
CONFIDENCE INTERVAL = 90 = Z VALUE OF 1.282
STANDARD DEVIATION = 10
DUE DATE = 40 + (1.282 * 10) = 53
You have just used the network planning model for a county road resurfacing project and found...
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy)
Project management
Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...
At the Hard Rock Café, like many organizations, project management is a key planning tool. Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within 5-month planning horizon. Tomasso identifies activities, their immediate predecessors and time estimates as shown in the table below. As a chief project manager, you have been asked to prepare a report for your company. This report needs to address the concerns...
Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use...
Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those...
Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...
Question #1: Some of the tasks in this project can be done in
parallel. Prepare a diagram showing the required network of tasks
and define the critical path. What is the length of the project
without crashing? Do not just answer, but show the whole
process.
Question #2: If the critical path is longer than 29 days, what
is the least additional amounting that Dr. Watage can spend and
still achieve this schedule objective (29 days)? Do not just
answer,...
39. Consider the following project, and answer the next 5 questions based on this data: Task ID Duration (Days) Predecessors 2 70 - 3 30 2 4 120 3 5 120 2 6 120 5 7 120 3,6 8 150 3,6 9 115 3,6 10 130 7,9 11 90 7,9 12 30 7,9 13 120 7,9 14 75 10 15 30 14 16 85 6 17 165 16 18 90 16 19 90 17,18 20 20 8,11,13,15,19 What is the...
Group Project Financial Planning A local dym just went corporate, so you decide to investigate its profitabit to see if it stock is worth buying. The gym collect a flat toe of 50 per month from each of its 63 members, but it's maintenance expenses are $170 per month plus an additional $0.15 every time someone uses the gym. The gym has created a solid model they use to predict how much use they get over the year U(m) =...
You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...