Question

2. You are in charge of planning and coordinating next falls sales management training program ur company. You have never do
f. If you want a 99% probability of completing the project on time, how far ahead of the scheduled meeting should you begin w
2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo your BUS 190 class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below: Task completion time estimate (weeks) Most Immediate Variance Task Predecessor Optimistic probable Pessimistic Mean 2.5 1.5 2.5 2.5 1.5 1.5 B,D0.5 B,D F,H 3.5 1.5 Fill in the values for the mean task time in the appropriate column. Show the formula you used below a. b. On the next page, draw the CPM/PERT diagram, filling in the values for the task times earliest and latest start and finish. What is the expected project completion time? c. What is the critical path? d. e. Calculate the appropriate variances in the table above. What is the overall project variance? What is the overall project SD?
f. If you want a 99% probability of completing the project on time, how far ahead of the scheduled meeting should you begin working on the project?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

hne eghml mean Es D (2)+2.5 2.5-1 2 244003 2-5 13 2 3 0-1085 е 0.02487 o. 02.74町 S,D S0.33 CA ih 0 02739C2 D (2 仁(D 831-to18900221 灿.J&999

Add a comment
Know the answer?
Add Answer to:
2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo yo...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (15. Doug Casey is in charge of planning and coordinating next spring's sales management training program...

    (15. Doug Casey is in charge of planning and coordinating next spring's sales management training program for his company. Doug listed the following activity information for this project: Immediate Predecessor M Time (weeks) Most Probable Activity Optimistic 1.5 2.0 Pessimistic 2.5 2.0 2.5 6.0 2.0 Description Plan topic Obtain speakers List meeting locations Select location Finalize speaker travel plans Make final check with speakers Prepare and mail brochure Take reservations Handle last-minute details BD Ε B, D G F, H...

  • Use Excel and show formulas used From the given table of activities and associated times, create...

    Use Excel and show formulas used From the given table of activities and associated times, create a PERT/CPM diagram and complete the forward and backward passes Immediate Predecessor ActivityDescription Critical Path = Prepare Blue Print Receive Permits Prepare Ground Create Press ReleaseB Cement Work Steel Work Cut Ribbon Ceremony E Total Project Time C,D Pessimistic PERT Time Most Probable 17 12 4 Activit Optimistic 26 13 16 12 12 13

  • PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

    PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....

  • The ABC Manufacturing Co. has made a decision to replace an existing production line with new...

    The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished. Activity predecessor Optimistic Most likely Pessimistic Expected A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

  • at PBI airport. The table aso provides the immedate predecessor event for each activity and the...

    at PBI airport. The table aso provides the immedate predecessor event for each activity and the optimistic [ol, most lkely Iml and pessimistic ipl time estimates ACTIITY ain Financing B Hire Marketing Outfe C. identity Recrutment Firm Remodel terminal F. Update SWA Website to indlude ights to/trom P G. Set-up Network & Technollogy at PB H Punchane /set-up new furniture /sinage L Launch Marketine Campaign K. Develop Processes& Procedures for Check in& Boarding L Post Job Openings M. Interview&Hire PBl...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT